2MAPPS v3.0
2MAPPS v3.0 Development and Processing Schedule




2MASS Final Data Processing and Release Schedule               
-------------------------------------------------------------------------------

ACTIVITY                                                        PLAN    ACTUAL

I. Observatory Operations

End of northern ops                                         11/30/00  12/01/00
End of southern ops                                          1/31/01   2/15/01


II. Data Processing and Catalog Generation

End of northern preliminary data processing                 12/15/00  12/08/00
Working DB northern data loading complete                   12/29/00  12/18/00
End of southern preliminary data processing                  2/16/01   3/01/01
Working DB southern data loading complete                    2/28/01   3/06/01

Selection criteria for final processing complete            12/15/00   6/01/01

Pre-processing tasks 

  Array Saturation Maps           - Preliminary                       12/13/00
				  - Final                    3/01/01  12/13/00
  Super darks/flats               - Preliminary                        2/15/01
				  - Final                    3/01/01   3/27/01
  Generate super .fpos files      - Preliminary      8/07/00-3/31/01   2/01/01
				  - Final                    3/01/01   7/31/01
  Extended source class. training - Preliminary
				  - Final                    3/01/01   1/17/01
  Production PSFs                 - Preliminary                        3/01/01
				  - Final                    3/01/01   3/19/01
  MAPCOR normalization tables     - Preliminary                        2/14/01
			          - Final                    3/01/01   3/15/01
  MAPCOR artifact parameters      - Preliminary                        1/15/01
				  - Final                    3/01/01   7/21/01
  Final secondary standards                                  3/01/01   5/11/01
  Final sets of minor planet and   
    comet ephemerides                                        3/01/01   3/19/01

Final uniform data processing begins                         4/01/01   8/02/01
Final product generation begins                             11/01/01   
Final uniform data processing ends                           3/31/02  [2/10/01]
Final product generation complete                            9/01/02  


III. 2MAPPS v3.0 Development and Test

2MAPPS v3.0 PDR                                              6/14/00  ongoing
2MAPPS v3.0 subsystem development schedules due              9/27/00  9/27/00
2MAPPS v3.0 SIS lists due                                    9/27/00  9/27/00
First versions of 2MAPPS v3.0 SIS's due                     10/11/00 10/11/00
First v3.0 Subsystem Deliveries                             11/15/00 11/21/00
Integration and test/system debugging begins                11/16/00 11/22/00
Timing test and hardware upgrade decision point             12/11/00  7/15/01 
Final Processing OPS plan         - Preliminary              1/24/01 11/29/00
                                  - Final                    2/15/01  2/15/01
Dry run processing                                  2/01/01-2/28/01 6/27-8/13/01
Analysis to validate dry run processing             2/01/01-3/15/01 6/27-9/30/01
Final processing readiness review                            3/01/01 7/01-8/01
Final uniform processing begins                              4/01/01   8/2/01


IV. Final Product Generation

Preliminary catalog selection criteria                       9/01/01 [11/30/01]
Begin Test Catalog Generation                               12/12/01
Analysis of Test Catalog                                1/05-2/15/02
Final catalog selection criteria                              2/1/02
Final product generation begins                             11/01/01  [2/15/02] 
Final product generation complete                            6/15/02
Final Product Analysis and Validation                   4/01-9/30/02
Documentation Preparation and Review Complete                9/01/02


V. Data Release

IRSA preparation (update menus, install catalogs, 
     image metadata tables, index, build xpf files)          7/01/02
IRSA Interface Validation                                    9/01/02
FTP Tables In-place                                          9/01/02
FTP Versions Validation        
DVD Production Complete                                     10/15/02

Final 2MASS Catalogs and Atlas Release                       9/10/02

Working DB                                                  TBD
Calibration DB                                              TBD
Deep Exposures                                              TBD
Extended user support                                       TBD



Last Updated: 2 November 2001
R. Cutri - IPAC